Germany Cuts Solar Subsidy
By Dr. Till Vogel
The German federal cabinet decided in early March to reduce feed-in tariffs for newly-built solar photovoltaic projects in Germany by an average of 15% starting July 1, 2010. Another 9% is already scheduled to take place on January 1, 2011.
The plan must still be approved by the Bundestag, or the German parliament. Some changes are possible before the bill implementing the plan is approved
The lower tariffs will apply to projects that go into service on or after the dates set for tariff reductions.
The tariffs were already cut by 9% at the start of 2010. They currently run from 37.14¢ to 28.43¢ a kilowatt hour depending on the size of the project and its location. The feed-in tariff is the amount that utilities in Germany are required by law to pay for electricity offered to them — in this case from photovoltaic facilities. Total installed generating capacity from solar in Germany is 8,877 megawatts from photovoltaic installations. There are currently no concentrating solar power projects (also known as solar thermal). The tariff is the same for both types of solar.
The feed-in tariffs have been declining over time, but they normally decline only once every year. When Germany first instituted them in 2000, they were 62.4¢ per kWh.
The latest plan would lead to a total reduction in the feed-in tariff for PV energy of almost 30% within a 13-month period. As the feed-in tariff is guaranteed by law for the year of the connection to the grid plus the following 20 calendar years, the amount is important for financing PV projects. The latest measures mean a significant loss of revenue over 20 years if a project starts too late.
Reductions Vary
The feed-in tariffs for electricity generated in roof-mounted solar systems will be reduced by 16% if the system is connected to the grid after June 2010. The relevant date for the calculation of the feed-in tariff for a German PV project under the regime of subsidies is the day of the first power supply into the grid. Thus, commencing power sales on July 1 rather than June 30 can cost a developer a lot of money.
The reduction of the feed-in tariffs for electricity from ground-mounted PV systems installed on so-called redeveloped areas -– for example, former military sites or former landfills -– is not as painful as for roof-mounted systems. The reason for this is purely political. The intention is to promote the use of such real estate for PV systems as they are of limited use for other purposes. Furthermore, the investors run the risk of having to deal with environmental pollution on such sites. Thus, the reduction of the feed-in tariffs for projects in such locations is only 11%.
For other areas, the tariff will be reduced by 15%.
Feed-in tariffs will be eliminated for ground-mounted PV systems installed in areas that are defined as “farm land.” This has been a subject of intensive discussion. Opponents argue that it is unethical to produce electricity on land that could feed humans while people starve and prices for food rise. From July 1, 2010 on, there will no longer be an obligation for grid operators to buy and remunerate solar companies using “farm land” to generate electricity. Since there are a lot of projects already in the pipeline, there needs to be a transition arrangement for these projects. The bill provides “grandfather” relief. The current tariff would continue to apply to projects that are already in an advanced stage of development, were approved by the local authorities by an official development plan before the end of 2009 (although this date is currently under discussion) and will be built and connected to the grid by the end of 2010.
In order to compensate for the loss of “farm land” for solar development, the cabinet suggested that trade and industrial areas as well as areas along motorways and railways (the latter in 100- to 200-meter-wide strips) should be included on the list of areas on which PV systems can claim special promotion under German law. Systems in such areas will be eligible for the feed-in tariff in the future.
Although such changes in the guaranteed feed-in tariffs have been foreseeable since the current black-yellow government formed its coalition in Berlin, the amount of the reduction is surprising.
Also the complete ban of ground-mounted PV systems on “farm land” was unexpected.
The German PV industry now claims that it is being strangled and that the number and size of new PV projects in Germany will drop significantly with a cost of thousands of jobs in the national PV industry. The government responds that since the price of solar power equipment (especially solar modules) dropped significantly during the last 18 months, solar projects have become more profitable leading to an “over-promotion” of new projects by the current tariffs.
Under the German law, the local grid operator has to connect every PV plant to its grid and to purchase all electricity generated as well as to pay the feed-in tariffs provided for by law. German law guarantees a constant feed-in tariff for the year in which the plant starts to supply electricity into the grid and the following 20 calendar years. The details are in an “Act on Granting Priority to Renewable Energy Sources.” The grid operator can pass through all these amounts to its customers as an add-on fee to the regular electricity invoices. Thus, the subsidies are paid ultimately by all electricity consumers in Germany. To the extent electricity from solar costs more than from other sources, this becomes a burden on the German economy. The current German government wants to slow the rate at which Germany is adding to this burden by cutting tariffs which, in turn, will mean fewer new projects.
Lobbyists from the solar industry have mobilized and are working on the politicians from both partners of the black-yellow coalition in Berlin. These efforts have already met with some success: only two weeks after the declaration by the federal cabinet, the prime minister of Bavaria — which is one of the southern states and thus hosts more solar projects than any other state in Germany — demanded changes in the federal plan. Perhaps surprisingly, it appears that the coalition is willing to follow this demand and will provide for a longer transition period to allow projects that are currently under development to be completed under the existing tariff. More changes are possible before any plan is adopted by the Bundestag.
Significance?
So what does all this mean for investors and banks who are engaged in the PV business in Germany?
For those who have German PV projects in the pipeline, the best advice is to watch the legislative process closely and try to qualify for grandfather relief under whatever transition rule is adopted. Currently the bill states that PV plants already operating are not affected at all by the changes. It should be safe to assume that this will not change. Any retroactive reduction in tariffs would be declared unconstitutional by the federal constitutional court.
Also, PV plants that start to feed energy into the grid before the key dates (July 1, 2010 or possibly October 1, 2010) will not be affected by the changes for the same reasons.
Only plants that start to feed electricity on or after July 1, 2010 (or whatever date is chosen ultimately) are affected by the new tariffs. As the construction period for a PV project is in some cases longer than the three months remaining until July, this means that some projects that were planned, calculated, funded and developed under the old feed-in regime could be hit hard. Developers in such a position will have to decide whether to start construction or cancel their projects.
To soften the hardship, the bill grants a grace period for very large countryside projects that are already under development. Such projects can be built and connected to the grid until the end of this year and still receive the existing feed-in tariff until 2030 if the competent local parliament had already agreed to the project by December 31, 2009 and has granted the permission to build the plant. However, for all other types of PV projects, especially the very popular roof-mounted systems, this transition rule will not apply. Therefore, there is now tremendous time pressure to finish construction of these projects before July 1, 2010. In case of some large projects, this will not be possible.
Upside
The bill is not only a one-way street. It increases some subsidies.
Under the current German regime, there is a financial incentive for owners of smaller PV plants (such as private households) not to feed the electricity into the grid but to use the energy for themselves on site. If an owner does so, he receives an incentive payment from his grid operator. The owner receives this money and also avoids having to buy electricity from the grid. Thus, householders are better off than if they sold to the grid. The bill increases this incentive from 3.6¢ to 8¢ per kWh. The incentive will also be extended to larger PV systems with outputs of up to 800 kilowatts. However, the incentive payments to owners of such larger systems are reduced to the extent the price the homeowner would be charged to buy electricity from the grid is less than 20¢ a kWh. This is the benchmark price in the bill.
Further reductions in the feed-in tariff will occur at the rate of 9% a year. However, the rate could increase to 11% a year if additionally installed PV capacity reaches 3,500 megawatts a year. The national target for the growth of PV capacity in Germany is being raised from 1,700 megawatts to 3,500 megawatts per year. Once the growth of installed PV capacity exceeds 3.500 megawatts, then the feed-in tariffs will be reduced automatically by an additional 2% a year on top of the 9% annual reduction. On top of the scheduled reduction of 9%, tariffs will be reduced at the end of 2011 by another 3% for every 1,000 megawatts of additional growth in PV capacity above the national target. On the other hand, the bill provides that if the market growth in production capacity leaves Germany below a minimum limit of 2,500 megawatts per year, then the feed-in tariffs decrease more slowly. The 9% normal rate of reduction would be shaved by 2.5% for every 500 megawatts that installed capacity is below the minimum limit.